Waterway Guide reserves the option of editing reviews and comments for grammar, clarity and the removal of defamatory or potentially slanderous language. All equipment should be removed from the area by September 30, 2023. Work is scheduled to be completed by AugwithĮquipment breakdown shortly after. Dredge will operate 5 days a week, 12 hours a day, weather permitting and we will monitor VHF-FM channel 08. The pipeline will be continuously marked with orange buoys. In addition to the dredge, 4 small work skiffs, 4 miles of pipeline from the dredge to the spoil site and two anchor barges as well as two booster pumps will be utilized. Equipment will be on site starting Jand anticipated dredging will begin the week of June 26, 2023. will begin the dredging of Herring Bay and Rockhold Creek, beginning in the Herring Bay and working their way into Rockhold Creek. View in Waterway Explorer MD: Herring Bay, Rockhold Creek, Dredging